Dept. of Trans. PROGRESS Serial No. Contract No. 07-052-13-48 11-072804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 4% 27% 11-SD-78-3.2/5.0 Federal Project: NONE Progress payment No. 03 Payment period ending: 02-20-07 SIM J HARRIS INC P O BOX 420850 SAN DIEGO CA 921420850 Escrow No. 02272 Total Estimate This Estimate 1. Contract Itms Without Mobil. 401,241.72 186,671.92 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 401,241.72 186,671.92 5. Mobilization 6. Total Work Completed 401,241.72 7. Deductions 0.00 3,514.78 8. a.Contract Retentions -40,124.17 -18,667.19 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 361,117.55 171,519.51 10. Reduction Amt to Escrow 11. Payment to Escrow 40,120.00 12. Net Pymt. this Estimate 171,519.51