Dept. of Trans. PROGRESS Serial No. Contract No. 07-080-14-17 11-072804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 4% 27% 11-SD-78-3.2/5.0 Federal Project: NONE Progress payment No. 04 Payment period ending: 03-20-07 SIM J HARRIS INC P O BOX 420850 SAN DIEGO CA 921420850 Escrow No. 02272 Total Estimate This Estimate 1. Contract Itms Without Mobil. 472,635.04 71,393.32 2.a. Extra Work b. Adjustment Comp. -277.58 -277.58 3. Materials on Hand 4. Earned Subject to Retention 472,357.46 71,115.74 5. Mobilization 6. Total Work Completed 472,357.46 7. Deductions 8. a.Contract Retentions -47,235.75 -7,111.58 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 425,121.71 64,004.16 10. Reduction Amt to Escrow 11. Payment to Escrow 47,230.00 12. Net Pymt. this Estimate 64,004.16