Dept. of Trans. PROGRESS Serial No. Contract No. 07-143-06-50 11-072804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 12% 27% 11-SD-78-3.2/5.0 Federal Project: NONE Progress payment No. 06 Payment period ending: 05-20-07 SIM J HARRIS INC P O BOX 420850 SAN DIEGO CA 921420850 Escrow No. 02272 Total Estimate This Estimate 1. Contract Itms Without Mobil. 802,680.28 96,286.40 2.a. Extra Work 10,991.75 7,753.05 b. Adjustment Comp. -553.06 0.00 3. Materials on Hand 4. Earned Subject to Retention 813,118.97 104,039.45 5. Mobilization 524,980.20 0.00 6. Total Work Completed 1,338,099.17 7. Deductions -9,628.64 -9,628.64 8. a.Contract Retentions -81,311.90 -10,403.95 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,247,158.63 84,006.86 10. Reduction Amt to Escrow 11. Payment to Escrow 81,310.00 12. Net Pymt. this Estimate 84,006.86