Dept. of Trans. PROGRESS Serial No. Contract No. 07-233-15-14 11-072804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 78% 83% 11-SD-78-3.2/5.0 Federal Project: NONE Progress payment No. 09 Payment period ending: 08-20-07 SIM J HARRIS INC 4375 JUTLAND DR, STE. 200 SAN DIEGO CA 92117 Escrow No. 02272 Total Estimate This Estimate 1. Contract Itms Without Mobil. 7,863,739.04 2,613,546.89 2.a. Extra Work 57,585.12 5,976.04 b. Adjustment Comp. -8,820.94 0.00 3. Materials on Hand 4. Earned Subject to Retention 7,912,503.22 2,619,522.93 5. Mobilization 1,049,960.40 52,498.02 6. Total Work Completed 8,962,463.62 7. Deductions -42,817.14 10,871.76 8. a.Contract Retentions -395,625.16 -130,976.15 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 8,524,021.32 2,551,916.56 10. Reduction Amt to Escrow 11. Payment to Escrow 395,620.00 12. Net Pymt. this Estimate 2,551,916.56