Dept. of Trans. SUPPLEMENTAL Serial No. Contract No. 01-184-09-30 11-076304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 66% 74% 11-SD-805-8.6/17.5 Federal Project: ACIM-805-1(580) Progress payment No. 08 Payment period ending: 06-20-01 HAZARD CONSTRUCTION COMPANY AND PAVEMENT SPECIALISTS INCORPORATED A JOINT VENTURE P O BOX 229000 SAN DIEGO CA 921922000 Escrow No. 01684 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,764,735.22 0.00 2.a. Extra Work 44,832.63 2,598.51 b. Adjustment Comp. 10,138.81 0.00 3. Materials on Hand 175,774.00 175,774.00 4. Earned Subject to Retention 3,995,480.66 178,372.51 5. Mobilization 440,000.00 0.00 6. Total Work Completed 4,259,706.66 7. Deductions -20,000.00 0.00 8. a.Contract Retentions -199,774.03 -8,918.62 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 4,215,706.63 169,453.89 10. Reduction Amt to Escrow 11. Payment to Escrow 199,770.00 12. Net Pymt. this Estimate 169,453.89