Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 02-063-10-23 11-076304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 11-SD-805-8.6/17.5 Federal Project: ACIM-805-1(580) Progress payment No. 16 Payment period ending: 11-14-01 HAZARD CONSTRUCTION COMPANY AND PAVEMENT SPECIALISTS INCORPORATED A JOINT VENTURE P O BOX 229000 SAN DIEGO CA 921929000 Escrow No. 01684 Total Estimate This Estimate 1. Contract Itms Without Mobil. 5,043,782.43 7,000.00 2.a. Extra Work 351,132.26 123,727.52 b. Adjustment Comp. 47,899.34 30,045.50 3. Materials on Hand 4. Earned Subject to Retention 5,442,814.03 160,773.02 5. Mobilization 440,000.00 0.00 6. Total Work Completed 5,882,814.03 7. Deductions -21,125.15 11,000.00 8. a.Contract Retentions -260,673.47 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 260,673.47 0.00 9. Total pay to Contractor 5,861,688.88 171,773.02 10. Reduction Amt to Escrow -260,670.00 0.00 11. Payment to Escrow 260,670.00 12. Net Pymt. this Estimate 171,773.02