Dept. of Trans. PROGRESS Serial No. Contract No. 15-083-06-21 11-076704 PROGRESS PAYMENT VOUCHER %complete: %time: 10% 26% Location: Federal Project: 11-IMP-5708 NONE Progress payment No. 006 Payment period ending: 03-20-15 HAL HAYS CONSTRUCTION INC 4181 LATHAM STREET RIVERSIDE CA 92501 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 622,700.88 83,931.31 2. a. Extra Work 358,072.50 71,614.50 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 980,773.38 155,545.81 5. Mobilization 6. Total Work Completed 980,773.38 7. Deductions -11,603.24 -5,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 969,170.14 150,545.81 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 150,545.81