Dept. of Trans. PROGRESS Serial No. Contract No. 05-144-13-25 11-077304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 2% 12% 11-SD-15-M13.0/R50.9 Federal Project: ACIM-015-4(197) Progress payment No. 02 Payment period ending: 05-20-05 HANSON SJH CONSTRUCTION P O BOX 639069 SAN DIEGO CA 921639069 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 100,875.42 56,907.42 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 100,875.42 56,907.42 5. Mobilization 6. Total Work Completed 100,875.42 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 100,875.42 56,907.42 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 56,907.42