Dept. of Trans. PROGRESS Serial No. Contract No. 06-025-06-41 11-078304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 28% 35% 11-SD-5-R42.7/R51.2 Federal Project: ACIM-005-1(600) Progress payment No. 03 Payment period ending: 01-20-06 F C I CONSTRUCTORS INC 2585 BUSINESS PARK DRIVE VISTA CA 920818831 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,994,938.25 1,251,627.08 2.a. Extra Work b. Adjustment Comp. -96,000.00 -96,000.00 3. Materials on Hand 4. Earned Subject to Retention 1,898,938.25 1,155,627.08 5. Mobilization 750,000.00 250,000.00 6. Total Work Completed 2,648,938.25 7. Deductions -10,000.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 2,638,938.25 1,405,627.08 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,405,627.08