Dept. of Trans. PROGRESS Serial No. Contract No. 06-081-13-03 11-078304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 64% 57% 11-SD-5-R42.7/R51.2 Federal Project: ACIM-005-1(600) Progress payment No. 06 Payment period ending: 03-20-06 F C I CONSTRUCTORS INC 2585 BUSINESS PARK DRIVE VISTA CA 920818831 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 5,280,409.00 890,983.30 2.a. Extra Work b. Adjustment Comp. -96,000.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 5,184,409.00 890,983.30 5. Mobilization 1,000,000.00 50,000.00 6. Total Work Completed 6,184,409.00 7. Deductions -10,000.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 6,174,409.00 940,983.30 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 940,983.30