Dept. of Trans. SUPPLEMENTAL Serial No. Contract No. 06-095-07-58 11-078304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 66% 57% 11-SD-5-R42.7/R51.2 Federal Project: ACIM-005-1(600) Progress payment No. 07 Payment period ending: 03-20-06 F C I CONSTRUCTORS INC 2585 BUSINESS PARK DRIVE VISTA CA 920818831 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 5,316,349.98 35,940.98 2.a. Extra Work b. Adjustment Comp. -96,000.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 5,220,349.98 35,940.98 5. Mobilization 1,000,000.00 0.00 6. Total Work Completed 6,220,349.98 7. Deductions -10,000.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 6,210,349.98 35,940.98 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 35,940.98