Dept. of Trans. PROGRESS Serial No. Contract No. 07-330-13-22 11-0786U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 87% 87% 11-SD-5-8.6/R10.0 Federal Project: ACIM-005-1(599) ACST-S054(7) P-S054(7) Progress payment No. 18 Payment period ending: 11-20-07 WESTERN RIM CONSTRUCTORS INC 912 S ANDREASEN DRIVE STE 108 ESCONDIDO CA 92029 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 4,186,064.35 14,605.62 2.a. Extra Work 463,047.57 -682.58 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 4,649,111.92 13,923.04 5. Mobilization 494,729.00 0.00 6. Total Work Completed 5,143,840.92 7. Deductions -27,618.48 -8.38 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 5,116,222.44 13,914.66 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 13,914.66