Dept. of Trans. PROGRESS Serial No. Contract No. 02-023-14-10 11-079204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 62% 43% 11-SD-54-3.6/5.6 Federal Project: NONE Progress payment No. 18 Payment period ending: 01-20-02 REYCO EROSION CONTROL 7030 HAWARDEN DRIVE RIVERSIDE CA 92506 Escrow No. 01570 Total Estimate This Estimate 1. Contract Itms Without Mobil. 281,916.38 5,011.39 2.a. Extra Work 8,698.79 0.00 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 290,615.17 5,011.39 5. Mobilization 35,000.00 0.00 6. Total Work Completed 325,615.17 7. Deductions -4,500.00 0.00 8. a.Contract Retentions -14,530.76 -250.57 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 306,584.41 4,760.82 10. Reduction Amt to Escrow 11. Payment to Escrow 14,530.00 12. Net Pymt. this Estimate 4,760.82