Dept. of Trans. PROGRESS Serial No. Contract No. 03-170-14-29 11-079504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP SAT 11-SD-78-35.7/35.8 Federal Project: ACST-P078(101) PE-P078(101) Progress payment No. 05 Payment period ending: 06-20-03 T B PENICK AND SONS INC 9747 OLSON DRIVE SAN DIEGO CA 92121 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 371,094.98 1,908.24 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 371,094.98 1,908.24 5. Mobilization 45,200.00 0.00 6. Total Work Completed 416,294.98 7. Deductions -21,000.00 -1,000.00 8. a.Contract Retentions -18,554.75 -95.41 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 376,740.23 812.83 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 812.83