Dept. of Trans. PROGRESS Serial No. Contract No. 15-054-12-43 11-080174 PROGRESS PAYMENT VOUCHER %complete: %time: 17% 50% Location: Federal Project: 11-SD-76-R7.3/12.0 HPLU-6211(127) Progress payment No. 003 Payment period ending: 02-20-15 ACCU CONSTRUCTION, INC. 2098 S. GRAND AVE. SUITE A SANTA ANA CA 92705 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 281,122.30 138,496.50 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 281,122.30 138,496.50 5. Mobilization 52,500.00 17,500.00 6. Total Work Completed 333,622.30 7. Deductions -4,000.00 -4,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 329,622.30 151,996.50 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 151,996.50