Dept. of Trans. PROGRESS Serial No. Contract No. 17-142-10-48 11-080234 PROGRESS PAYMENT VOUCHER %complete: %time: 20% 17% Location: Federal Project: 11-IMP-98-31.6/32.1 ACHS-CBIP-0(980) DEMO-5621-1(113) Progress payment No. 002 Payment period ending: 05-20-17 HAZARD CONSTRUCTION COMPANY 6465 MARINDUSTRY DR SAN DIEGO CA 92121 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 449,915.35 260,315.35 2. a. Extra Work 19,259.37 19,259.37 b. Adustment Comp. 136,412.40 136,412.40 3. Materials on Hand 30,050.90 30,050.90 4. Earned Subject to Retention 635,638.02 446,038.02 5. Mobilization 382,500.00 382,500.00 6. Total Work Completed 988,087.12 7. Deductions -10,000.00 -10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,008,138.02 818,538.02 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 818,538.02