Dept. of Trans. PROGRESS Serial No. Contract No. 21-232-15-03 11-080284 PROGRESS PAYMENT VOUCHER %complete: %time: 9% 1% Location: Federal Project: 11-IMP-98-32.1/32.5 ACNH-P098(29) PL16-6211(134) Progress payment No. 002 Payment period ending: 08-20-21 SPECTRUM CONSTRUCTION GROUP INC 16 GOODYEAR #140 IRVINE CA 92618 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 37,508.33 33,611.45 2. a. Extra Work b. Adustment Comp. 350,371.86 405.00 3. Materials on Hand 4. Earned Subject to Retention 387,880.19 34,016.45 5. Mobilization 255,312.50 0.00 6. Total Work Completed 643,192.69 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 643,192.69 34,016.45 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 34,016.45