Dept. of Trans. PROGRESS Serial No. Contract No. 06-325-13-21 11-080514 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 95% 100% 11-SD-5-52.8/ .0 Federal Project: NONE Progress payment No. 03 Payment period ending: 11-20-06 SIM J HARRIS INC P O BOX 420850 SAN DIEGO CA 921420850 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 349,365.42 8,307.70 2.a. Extra Work b. Adjustment Comp. -477.45 -477.45 3. Materials on Hand 4. Earned Subject to Retention 348,887.97 7,830.25 5. Mobilization 23,091.80 0.00 6. Total Work Completed 371,979.77 7. Deductions -2,398.48 101.52 8. a.Contract Retentions -17,444.40 -391.51 b. Unsatisfactory Prog. -391.51 -391.51 c. Reduction after 95% Comp. 9. Total pay to Contractor 351,745.38 7,148.75 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 7,148.75