Dept. of Trans. PROGRESS Serial No. Contract No. 09-055-14-09 11-080624 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 65% 94% 11-SD-5722 Federal Project: NONE Progress payment No. 07 Payment period ending: 02-20-09 FALCON GENERAL ENGINEERING INC 572 COLLYN STREET VISTA CA 92083 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 668,677.26 152,170.43 2.a. Extra Work 9,147.20 9,147.20 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 677,824.46 161,317.63 5. Mobilization 6. Total Work Completed 677,824.46 7. Deductions -10,000.00 -10,000.00 8. a.Contract Retentions -33,891.22 -8,065.88 b. Unsatisfactory Prog. -25,290.47 -8,065.88 c. Reduction after 95% Comp. 9. Total pay to Contractor 608,642.77 135,185.87 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 135,185.87