Dept. of Trans. PROGRESS Serial No. Contract No. 07-143-06-50 11-080804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 32% 61% 11-SD-5-R1.6/R45.4 Federal Project: NONE Progress payment No. 04 Payment period ending: 05-21-07 H M S CONSTRUCTION INC 1225 LINDA VISTA DRIVE SAN MARCOS CA 92078 Escrow No. 02286 Total Estimate This Estimate 1. Contract Itms Without Mobil. 860,038.44 328,121.96 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 860,038.44 328,121.96 5. Mobilization 43,700.00 9,200.00 6. Total Work Completed 903,738.44 7. Deductions -2,040.00 0.00 8. a.Contract Retentions -55,526.36 -2,334.71 b. Unsatisfactory Prog. -16,406.10 -16,406.10 c. Reduction after 95% Comp. 9. Total pay to Contractor 829,765.98 318,581.15 10. Reduction Amt to Escrow 11. Payment to Escrow 55,520.00 12. Net Pymt. this Estimate 318,581.15