Dept. of Trans. PROGRESS Serial No. Contract No. 07-297-14-17 11-080804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP SAT 11-SD-5-R1.6/R45.4 Federal Project: NONE Progress payment No. 09 Payment period ending: 10-20-07 H M S CONSTRUCTION INC 1225 LINDA VISTA DRIVE SAN MARCOS CA 92078 Escrow No. 02286 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,705,007.62 9,640.36 2.a. Extra Work 107,958.83 81,820.71 b. Adjustment Comp. -23,851.63 224.37 3. Materials on Hand 4. Earned Subject to Retention 2,789,114.82 91,685.44 5. Mobilization 46,000.00 0.00 6. Total Work Completed 2,835,114.82 7. Deductions -28,290.00 10,000.00 8. a.Contract Retentions -139,455.74 -4,584.27 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 2,667,369.08 97,101.17 10. Reduction Amt to Escrow 11. Payment to Escrow 139,450.00 12. Net Pymt. this Estimate 97,101.17