Dept. of Trans. PROGRESS Serial No. Contract No. 04-356-13-37 11-080904 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 40% 31% 11-SD-15-M19.0/M22.0 Federal Project: ACIM-015-4(191) CMST-6211(32) PL-6211(32) Progress payment No. 14 Payment period ending: 12-20-04 COFFMAN SPECIALTIES INC 4375 JUTLAND DR STE 260 SAN DIEGO CA 92117 Escrow No. 02150 Total Estimate This Estimate 1. Contract Itms Without Mobil. 15,800,172.85 1,263,569.73 2.a. Extra Work 584,950.40 113,811.67 b. Adjustment Comp. 11,185.48 0.00 3. Materials on Hand 64,165.50 -24,342.12 4. Earned Subject to Retention 16,460,474.23 1,353,039.28 5. Mobilization 4,651,419.45 0.00 6. Total Work Completed 21,047,728.18 7. Deductions -64,881.68 -1,760.00 8. a.Contract Retentions -939,180.42 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 20,107,831.58 1,351,279.28 10. Reduction Amt to Escrow 11. Payment to Escrow 939,180.00 12. Net Pymt. this Estimate 1,351,279.28