Dept. of Trans. PROGRESS Serial No. Contract No. 05-054-13-11 11-080904 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 44% 35% 11-SD-15-M19.0/M22.0 Federal Project: ACIM-015-4(191) CMST-6211(32) PL-6211(32) Progress payment No. 18 Payment period ending: 02-20-05 COFFMAN SPECIALTIES INC 4375 JUTLAND DR STE 260 SAN DIEGO CA 92117 Escrow No. 02150 Total Estimate This Estimate 1. Contract Itms Without Mobil. 17,515,244.01 974,193.15 2.a. Extra Work 764,128.21 40,910.26 b. Adjustment Comp. 11,185.48 0.00 3. Materials on Hand 309,604.00 173,229.38 4. Earned Subject to Retention 18,600,161.70 1,188,332.79 5. Mobilization 4,651,419.45 0.00 6. Total Work Completed 22,941,977.15 7. Deductions -28,327.96 6,553.72 8. a.Contract Retentions -939,180.42 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 22,284,072.77 1,194,886.51 10. Reduction Amt to Escrow 11. Payment to Escrow 939,180.00 12. Net Pymt. this Estimate 1,194,886.51