Dept. of Trans. FINAL Serial No. Contract No. 12-142-10-12 11-080904 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 11-SD-15-M19.0/M22.0 Federal Project: ACIM-015-4(191) CMST-6211(32) PL-6211(32) Progress payment No. 66 Payment period ending: 01-15-08 COFFMAN SPECIALTIES INC 9685 VIA EXCELENCIA, STE 260 SAN DIEGO, CA 92126 Escrow No. 02150 Total Estimate This Estimate 1. Contract Itms Without Mobil. 44,771,281.99 0.00 2.a. Extra Work 8,352,609.09 0.00 b. Adjustment Comp. 16,842,047.53 13,750,000.00 3. Materials on Hand 4. Earned Subject to Retention 69,965,938.61 13,750,000.00 5. Mobilization 4,896,231.00 0.00 6. Total Work Completed 74,862,169.61 7. Deductions -124,007.44 0.00 8. a.Contract Retentions -2,708,517.74 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 2,708,517.74 0.00 9. Total pay to Contractor 74,738,162.17 13,750,000.00 10. Reduction Amt to Escrow -2,708,510.00 0.00 11. Payment to Escrow 2,708,510.00 12. Net Pymt. this Estimate 13,750,000.00