Dept. of Trans. PROGRESS Serial No. Contract No. 06-234-14-32 11-080914 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 59% 56% 11-SD-15-M22.0/M24.1 Federal Project: ACIM-015-4(192) CMST-6211(34) PL-6211(34) Progress payment No. 25 Payment period ending: 08-20-06 F C I CONSTRUCTORS BALFOUR BEATTY A JOINT VENTURE 2585 BUSINESS PARK DRIVE VISTA CA 920818831 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 34,454,674.05 2,315,954.71 2.a. Extra Work 955,262.11 109,245.00 b. Adjustment Comp. 949,791.05 599,807.78 3. Materials on Hand 602,758.29 -232,300.05 4. Earned Subject to Retention 36,962,485.50 2,792,707.44 5. Mobilization 6,700,000.00 0.00 6. Total Work Completed 43,059,727.21 7. Deductions -61,066.38 -1,140.00 8. a.Contract Retentions -1,848,124.28 -139,635.38 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 41,753,294.84 2,651,932.06 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,651,932.06