Dept. of Trans. PROGRESS Serial No. Contract No. 08-204-08-11 11-080914 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP SAT 11-SD-15-M22.0/M24.1 Federal Project: ACIM-015-4(192) CMST-6211(34) PL-6211(34) Progress payment No. 51 Payment period ending: 07-20-08 F C I CONSTRUCTORS BALFOUR BEATTY A JOINT VENTURE 1770 LA COSTA MEADOWS DR SAN MARCOS, CA 92009 Escrow No. 02185 Total Estimate This Estimate 1. Contract Itms Without Mobil. 61,968,267.13 324,990.89 2.a. Extra Work 4,553,088.47 113,948.47 b. Adjustment Comp. 2,488,657.37 357,996.50 3. Materials on Hand 151,581.17 -288,698.56 4. Earned Subject to Retention 69,161,594.14 508,237.30 5. Mobilization 6,700,000.00 0.00 6. Total Work Completed 75,710,012.97 7. Deductions -105,359.04 10,000.00 8. a.Contract Retentions -3,458,079.71 -25,411.87 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 72,298,155.39 492,825.43 10. Reduction Amt to Escrow 11. Payment to Escrow 3,458,070.00 12. Net Pymt. this Estimate 492,825.43