Dept. of Trans. PROGRESS Serial No. Contract No. 09-022-13-55 11-080914 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP SAT 11-SD-15-M22.0/M24.1 Federal Project: ACIM-015-4(192) CMST-6211(34) PL-6211(34) Progress payment No. 58 Payment period ending: 01-20-09 F C I CONSTRUCTORS BALFOUR BEATTY A JOINT VENTURE 1770 LA COSTA MEADOWS DR SAN MARCOS, CA 92078 Escrow No. 02185 Total Estimate This Estimate 1. Contract Itms Without Mobil. 61,932,660.16 -3,425.83 2.a. Extra Work 5,427,686.61 119,317.42 b. Adjustment Comp. 2,884,434.72 141,322.17 3. Materials on Hand 226,108.86 -98,459.11 4. Earned Subject to Retention 70,470,890.35 158,754.65 5. Mobilization 6,700,000.00 0.00 6. Total Work Completed 76,944,781.49 7. Deductions -97,695.66 -693.03 8. a.Contract Retentions -3,523,544.52 -7,937.73 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 73,549,650.17 150,123.89 10. Reduction Amt to Escrow 11. Payment to Escrow 3,523,540.00 12. Net Pymt. this Estimate 150,123.89