Dept. of Trans. SUPPLEMENTAL Serial No. Contract No. 06-180-09-22 11-080924 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 40% 35% 11-SD-15-M24.0/M26.5 Federal Project: ACIM-015-4(196) Progress payment No. 23 Payment period ending: 06-20-06 F C I CONSTRUCTORS BALFOUR BEATTY A JOINT VENTURE 2585 BUSINESS PARK DRIVE VISTA CA 920818831 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 24,559,353.34 120,000.00 2.a. Extra Work 759,604.71 -1,322.36 b. Adjustment Comp. 2,917,877.01 0.00 3. Materials on Hand 1,849,892.91 39,785.84 4. Earned Subject to Retention 30,086,727.97 158,463.48 5. Mobilization 7,790,000.00 0.00 6. Total Work Completed 36,026,835.06 7. Deductions -157,167.02 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 37,719,560.95 158,463.48 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 158,463.48