Dept. of Trans. SUPPLEMENTAL Serial No. Contract No. 06-276-11-03 11-080924 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 47% 40% 11-SD-15-M24.0/M26.5 Federal Project: ACIM-015-4(196) Progress payment No. 27 Payment period ending: 09-20-06 F C I CONSTRUCTORS BALFOUR BEATTY A JOINT VENTURE 2585 BUSINESS PARK DRIVE VISTA CA 920818831 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 30,085,382.21 0.00 2.a. Extra Work 914,857.93 0.00 b. Adjustment Comp. 2,989,319.15 0.00 3. Materials on Hand 1,913,945.91 900,000.00 4. Earned Subject to Retention 35,903,505.20 900,000.00 5. Mobilization 7,790,000.00 0.00 6. Total Work Completed 41,779,559.29 7. Deductions -187,392.53 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 43,506,112.67 900,000.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 900,000.00