Dept. of Trans. PROGRESS Serial No. Contract No. 07-204-13-55 11-080924 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 74% 57% 11-SD-15-M24.0/M26.5 Federal Project: ACIM-015-4(196) Progress payment No. 37 Payment period ending: 07-20-07 F C I CONSTRUCTORS BALFOUR BEATTY A JOINT VENTURE 2585 BUSINESS PARK DRIVE VISTA CA 920818831 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 53,091,172.79 1,555,548.96 2.a. Extra Work 1,824,237.42 131,821.05 b. Adjustment Comp. 3,916,532.05 3,656.81 3. Materials on Hand 1,809,016.93 -64,022.21 4. Earned Subject to Retention 60,640,959.19 1,627,004.61 5. Mobilization 8,200,000.00 0.00 6. Total Work Completed 67,031,942.26 7. Deductions -269,142.73 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 68,571,816.46 1,627,004.61 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,627,004.61