Dept. of Trans. SUPPLEMENTAL Serial No. Contract No. 08-211-13-40 11-080924 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 92% 77% 11-SD-15-M24.0/M26.5 Federal Project: ACIM-015-4(196) Progress payment No. 50 Payment period ending: 07-20-08 F C I CONSTRUCTORS BALFOUR BEATTY A JOINT VENTURE 1770 LA COSTA MEADOWS DR SAN MARCOS, CA 92009 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 69,269,807.29 0.00 2.a. Extra Work 3,245,824.69 0.00 b. Adjustment Comp. 5,108,376.34 500,000.00 3. Materials on Hand 199,473.27 0.00 4. Earned Subject to Retention 77,823,481.59 500,000.00 5. Mobilization 8,200,000.00 0.00 6. Total Work Completed 85,824,008.32 7. Deductions -307,809.11 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 85,715,672.48 500,000.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 500,000.00