Dept. of Trans. PROGRESS Serial No. Contract No. 08-268-09-17 11-080924 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 96% 79% 11-SD-15-M24.0/M26.5 Federal Project: ACIM-015-4(196) Progress payment No. 52 Payment period ending: 09-20-08 F C I CONSTRUCTORS BALFOUR BEATTY A JOINT VENTURE 1770 LA COSTA MEADOWS DR SAN MARCOS, CA 92078 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 71,159,864.20 673,542.17 2.a. Extra Work 3,938,255.32 438,740.87 b. Adjustment Comp. 6,202,248.22 561,592.24 3. Materials on Hand 0.00 -84,507.36 4. Earned Subject to Retention 81,300,367.74 1,589,367.92 5. Mobilization 8,200,000.00 0.00 6. Total Work Completed 89,500,367.74 7. Deductions -339,588.97 -11,779.86 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 89,160,778.77 1,577,588.06 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,577,588.06