Dept. of Trans. FINAL Serial No. Contract No. 13-009-08-43 11-080924 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 11-SD-15-M24.0/M26.5 Federal Project: ACIM-015-4(196) Progress payment No. 71 Payment period ending: 11-03-09 MALCOLM DRILLING COMPANY INC 92 NATOMA STREET, SUITE 400 SAN FRANCISCO, CA 94105 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 72,169,505.91 0.00 2.a. Extra Work 5,004,416.87 0.00 b. Adjustment Comp. 16,125,519.64 8,032,876.71 3. Materials on Hand 4. Earned Subject to Retention 93,299,442.42 8,032,876.71 5. Mobilization 8,200,000.00 0.00 6. Total Work Completed 101,499,442.42 7. Deductions -255,997.35 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 101,243,445.07 8,032,876.71 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 8,032,876.71