Dept. of Trans. PROGRESS Serial No. Contract No. 06-025-06-46 11-080934 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 23% 30% 11-SD-15-M18.9/M19.5 Federal Project: ACIM-015-4(200) ACST-P056(2) P-P056(2) Progress payment No. 09 Payment period ending: 01-20-06 F C I CONSTRUCTORS INC 2585 BUSINESS PARK DRIVE VISTA CA 920818831 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 4,999,995.21 801,592.66 2.a. Extra Work 48,816.84 23,906.75 b. Adjustment Comp. 4,580.59 0.00 3. Materials on Hand 20,637.10 20,637.10 4. Earned Subject to Retention 5,074,029.74 846,136.51 5. Mobilization 2,325,000.00 0.00 6. Total Work Completed 7,378,392.64 7. Deductions 0.00 10,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 7,399,029.74 856,136.51 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 856,136.51