Dept. of Trans. PROGRESS Serial No. Contract No. 08-144-13-42 11-080934 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 95% 100% 11-SD-15-M18.9/M19.5 Federal Project: ACIM-015-4(200) ACST-P056(2) P-P056(2) Progress payment No. 38 Payment period ending: 05-20-08 F C I CONSTRUCTORS INC 1770 LA COSTA MEADOWS DRIVE SAN MARCOS, CA 92009 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 28,874,729.92 584,159.07 2.a. Extra Work 2,702,624.32 524,912.35 b. Adjustment Comp. 217,177.68 -28,155.26 3. Materials on Hand 108,781.51 -165,408.39 4. Earned Subject to Retention 31,903,313.43 915,507.77 5. Mobilization 3,100,000.00 0.00 6. Total Work Completed 34,894,531.92 7. Deductions -103,268.92 -10,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 34,900,044.51 905,507.77 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 905,507.77