Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 08-268-08-41 11-080934 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 11-SD-15-M18.9/M19.5 Federal Project: ACIM-015-4(200) ACST-P056(2) P-P056(2) Progress payment No. 42 Payment period ending: 07-15-08 F C I CONSTRUCTORS INC 1770 LA COSTA MEADOWS DRIVE SAN MARCOS, CA 92078 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 29,356,614.13 -280,541.60 2.a. Extra Work 3,361,284.05 254,865.84 b. Adjustment Comp. 514,180.67 132,935.47 3. Materials on Hand 4. Earned Subject to Retention 33,232,078.85 107,259.71 5. Mobilization 3,100,000.00 0.00 6. Total Work Completed 36,332,078.85 7. Deductions -122,399.32 -16,930.40 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 36,209,679.53 90,329.31 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 90,329.31