Dept. of Trans. PROGRESS Serial No. Contract No. 07-268-06-46 11-080944 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 51% 50% 11-SD-15-M18.6/M27.7 Federal Project: ACIM-015-4(201) CMST-6211(50) PL-6211(50) Progress payment No. 15 Payment period ending: 09-20-07 F C I CONSTRUCTORS INC 2585 BUSINESS PARK DRIVE VISTA CA 920818831 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 17,739,546.61 1,387,442.89 2.a. Extra Work 539,797.47 57,760.48 b. Adjustment Comp. 292,244.68 309,416.94 3. Materials on Hand 135,972.99 59,808.22 4. Earned Subject to Retention 18,707,561.75 1,814,428.53 5. Mobilization 3,705,000.00 0.00 6. Total Work Completed 22,276,588.76 7. Deductions -11,475.28 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 22,401,086.47 1,814,428.53 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,814,428.53