Dept. of Trans. SUPPLEMENTAL Serial No. Contract No. 08-305-12-51 11-080944 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 87% 95% 11-SD-15-M18.6/M27.7 Federal Project: ACIM-015-4(201) CMST-6211(50) PL-6211(50) Progress payment No. 31 Payment period ending: 10-20-08 F C I CONSTRUCTORS INC 1770 LA COSTA MEADOWS DRIVE SAN MARCOS, CA 92078 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 35,359,180.75 47,235.30 2.a. Extra Work 3,248,066.91 44,624.26 b. Adjustment Comp. 1,126,097.76 6,661.36 3. Materials on Hand 1,873,759.88 0.00 4. Earned Subject to Retention 41,607,105.30 98,520.92 5. Mobilization 3,900,000.00 0.00 6. Total Work Completed 43,633,345.42 7. Deductions -72,782.08 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 45,434,323.22 98,520.92 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 98,520.92