Dept. of Trans. PROGRESS Serial No. Contract No. 09-202-14-40 11-080944 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 99% 100% 11-SD-15-M18.6/M27.7 Federal Project: ACIM-015-4(201) CMST-6211(50) PL-6211(50) Progress payment No. 40 Payment period ending: 07-20-09 FLATIRON WEST, INC. 1770 LA COSTA MEADOWS DRIVE SAN MARCOS, CA 92078 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 38,576,793.20 49,116.55 2.a. Extra Work 4,355,514.20 0.00 b. Adjustment Comp. 3,806,826.51 1,000,000.00 3. Materials on Hand 156,809.58 -997,147.04 4. Earned Subject to Retention 46,895,943.49 51,969.51 5. Mobilization 3,900,000.00 0.00 6. Total Work Completed 50,639,133.91 7. Deductions -2,782.08 1,481.46 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 50,793,161.41 53,450.97 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 53,450.97