Dept. of Trans. PROGRESS Serial No. Contract No. 08-023-14-18 11-081104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 90% 100% 11-SD-5-R26.8/R26.8 Federal Project: NONE Progress payment No. 04 Payment period ending: 01-20-08 HAZARD CONSTRUCTION COMPANY P O BOX 229000 SAN DIEGO CA 921929000 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 593,339.65 223,053.20 2.a. Extra Work 454.98 454.98 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 593,794.63 223,508.18 5. Mobilization 70,000.00 0.00 6. Total Work Completed 663,794.63 7. Deductions -10,000.00 0.00 8. a.Contract Retentions -29,689.73 -11,175.41 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 624,104.90 212,332.77 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 212,332.77