Dept. of Trans. PROGRESS Serial No. Contract No. 03-296-10-46 11-081704 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 7% 20% 11-SD-125-R15.1/22.1 Federal Project: ACST-P125(15) PHG-P125(15) ACST-P125(15) Progress payment No. 01 Payment period ending: 10-20-03 C AND W CONSTRUCTION SPECIALTIES INC 2419 PALMA DRIVE VENTURA CA 93003 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 37,373.52 37,373.52 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 37,373.52 37,373.52 5. Mobilization 13,221.00 13,221.00 6. Total Work Completed 50,594.52 7. Deductions -3,358.80 -3,358.80 8. a.Contract Retentions -3,737.35 -3,737.35 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 43,498.37 43,498.37 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 43,498.37