Dept. of Trans. PROGRESS Serial No. Contract No. 04-055-14-41 11-081704 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 81% 87% 11-SD-125-R15.1/22.1 Federal Project: ACST-P125(15) PHG-P125(15) ACST-P125(15) Progress payment No. 04 Payment period ending: 02-20-04 C AND W CONSTRUCTION SPECIALTIES INC 2419 PALMA DRIVE VENTURA CA 93003 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 603,839.69 286,626.29 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 603,839.69 286,626.29 5. Mobilization 26,442.00 1,322.10 6. Total Work Completed 630,281.69 7. Deductions -13,358.80 0.00 8. a.Contract Retentions -30,191.98 -14,331.31 b. Unsatisfactory Prog. 0.00 9,517.08 c. Reduction after 95% Comp. 9. Total pay to Contractor 586,730.91 283,134.16 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 283,134.16