Dept. of Trans. PROGRESS Serial No. Contract No. 04-113-14-04 11-081704 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP SAT 11-SD-125-R15.1/22.1 Federal Project: ACST-P125(15) PHG-P125(15) ACST-P125(15) Progress payment No. 06 Payment period ending: 04-20-04 C AND W CONSTRUCTION SPECIALTIES INC 2419 PALMA DRIVE VENTURA CA 93003 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 721,107.97 40,703.47 2.a. Extra Work 13,472.74 2,125.55 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 734,580.71 42,829.02 5. Mobilization 26,442.00 0.00 6. Total Work Completed 761,022.71 7. Deductions -17,802.34 3,586.14 8. a.Contract Retentions -36,729.04 -2,141.46 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 706,491.33 44,273.70 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 44,273.70