Dept. of Trans. PROGRESS Serial No. Contract No. 18-110-17-08 11-085784 PROGRESS PAYMENT VOUCHER %complete: %time: 19% 16% Location: Federal Project: 11-SD-163-4.1/4.9 NONE Progress payment No. 007 Payment period ending: 04-20-18 FLATIRON WEST, INC. 1770 LA COSTA MEADOWS DR SAN MARCOS CA 92078 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,613,104.51 783,549.96 2. a. Extra Work 150,509.77 51,168.05 b. Adustment Comp. 10,803.93 8,971.34 3. Materials on Hand 73,560.30 73,560.30 4. Earned Subject to Retention 3,847,978.51 917,249.65 5. Mobilization 2,152,500.00 0.00 6. Total Work Completed 5,926,918.21 7. Deductions -9,000.00 -2,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 5,991,478.51 915,249.65 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 915,249.65