Dept. of Trans. PROGRESS Serial No. Contract No. 18-354-15-00 11-085784 PROGRESS PAYMENT VOUCHER %complete: %time: 42% 38% Location: Federal Project: 11-SD-163-4.1/4.9 NONE Progress payment No. 015 Payment period ending: 12-20-18 FLATIRON WEST, INC. 1770 LA COSTA MEADOWS DR SAN MARCOS CA 92078 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 9,979,824.94 460,062.27 2. a. Extra Work 531,579.74 130,727.18 b. Adustment Comp. 105,823.28 107,805.57 3. Materials on Hand 4. Earned Subject to Retention 10,617,227.96 698,595.02 5. Mobilization 2,726,500.00 0.00 6. Total Work Completed 13,343,727.96 7. Deductions -7,000.00 5,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 13,336,727.96 703,595.02 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 703,595.02