Dept. of Trans. PROGRESS Serial No. Contract No. 19-018-11-41 11-085784 PROGRESS PAYMENT VOUCHER %complete: %time: 44% 40% Location: Federal Project: 11-SD-163-4.1/4.9 NONE Progress payment No. 016 Payment period ending: 01-20-19 FLATIRON WEST, INC. 1770 LA COSTA MEADOWS DR SAN MARCOS CA 92078 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 10,425,637.14 445,812.21 2. a. Extra Work 575,263.67 43,683.93 b. Adustment Comp. 105,823.28 0.00 3. Materials on Hand 129,646.57 129,646.57 4. Earned Subject to Retention 11,236,370.66 619,142.71 5. Mobilization 2,726,500.00 0.00 6. Total Work Completed 13,833,224.09 7. Deductions -8,000.00 -1,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 13,954,870.66 618,142.71 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 618,142.71