Dept. of Trans. PROGRESS Serial No. Contract No. 19-233-17-00 11-085784 PROGRESS PAYMENT VOUCHER %complete: %time: 65% 58% Location: Federal Project: 11-SD-163-4.1/4.9 NONE Progress payment No. 023 Payment period ending: 08-20-19 FLATIRON WEST, INC. 1770 LA COSTA MEADOWS DR SAN MARCOS CA 92078 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 16,329,249.46 1,426,667.86 2. a. Extra Work 1,620,117.30 167,020.61 b. Adustment Comp. 133,481.19 12,064.40 3. Materials on Hand 489,156.06 -13,573.14 4. Earned Subject to Retention 18,572,004.01 1,592,179.73 5. Mobilization 2,870,000.00 0.00 6. Total Work Completed 20,952,847.95 7. Deductions -5,000.00 -1,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 21,437,004.01 1,591,179.73 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,591,179.73