Dept. of Trans. PROGRESS Serial No. Contract No. 20-018-08-55 11-085784 PROGRESS PAYMENT VOUCHER %complete: %time: 89% 89% Location: Federal Project: 11-SD-163-4.1/4.9 NONE Progress payment No. 028 Payment period ending: 01-20-20 FLATIRON WEST, INC. 16470 W. BERNARDO DR #120 SAN DIEGO CA 92127 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 24,186,838.22 431,146.08 2. a. Extra Work 2,131,502.84 32,459.98 b. Adustment Comp. 360,920.86 1,251.76 3. Materials on Hand 160,044.17 -3,473.50 4. Earned Subject to Retention 26,839,306.09 461,384.32 5. Mobilization 2,870,000.00 0.00 6. Total Work Completed 29,549,261.92 7. Deductions -10,000.00 -4,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 29,699,306.09 457,384.32 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 457,384.32