Dept. of Trans. PROGRESS Serial No. Contract No. 20-204-15-49 11-085784 PROGRESS PAYMENT VOUCHER %complete: %time: 95% 100% Location: Federal Project: 11-SD-163-4.1/4.9 NONE Progress payment No. 034 Payment period ending: 07-20-20 FLATIRON WEST, INC. 16470 W. BERNARDO DR #120 SAN DIEGO CA 92127 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 26,142,191.45 67,036.57 2. a. Extra Work 2,979,136.08 258,860.18 b. Adustment Comp. 664,359.86 35,207.81 3. Materials on Hand 83,218.18 0.00 4. Earned Subject to Retention 29,868,905.57 361,104.56 5. Mobilization 2,870,000.00 0.00 6. Total Work Completed 32,655,687.39 7. Deductions -10,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 32,728,905.57 361,104.56 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 361,104.56