Dept. of Trans. PROGRESS Serial No. Contract No. 20-262-17-40 11-085784 PROGRESS PAYMENT VOUCHER %complete: %time: 96% 100% Location: Federal Project: 11-SD-163-4.1/4.9 NONE Progress payment No. 036 Payment period ending: 09-20-20 FLATIRON WEST, INC. 16470 W. BERNARDO DR #120 SAN DIEGO CA 92127 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 26,084,806.35 -5,461.80 2. a. Extra Work 3,280,739.14 96,728.19 b. Adustment Comp. 664,359.86 0.00 3. Materials on Hand 0.00 -41,609.09 4. Earned Subject to Retention 30,029,905.35 49,657.30 5. Mobilization 2,870,000.00 0.00 6. Total Work Completed 32,899,905.35 7. Deductions -10,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 32,889,905.35 49,657.30 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 49,657.30